Case Studies PDF Print E-mail

Cementitious Protective Coating
Project:
  St Lukes WWT, Guild Park, Preston

Client:  Lancashire Care NHS Trust

Product/System:  Concrete Repair and Cementitious  Protective Coating

Size:  600m2


Problem:
  Over many years the concrete sewage tanks have suffered from chemical attack from the raw sewage stored before being processed.  Much of the concrete cover to the steel had been lost and areas of exposed steel reinforcement spalling concrete were in evidence.

Solution:  The tanks were emptied and the concrete cleaned to allow inspection of the substrate.  Areas of exposed steel were broken out and repaired with a high build polymer modified mortar.  Prior to the application of a highly chemical resistant thin section cementitious coating which reinstated the eroded concrete cover and provided a chemical resistant lining to the tanks.   Application of Coating   Drained sewage tank prior to works   

 








* * * * * * * * * *


st_james_school_blackburn_web.jpgProject:
  St. James C of E Primary School, Blackburn

Client:  Lancashire County Council

Product/System:  Tor Coatings Ltd - Elastaseal 10 Year System

Size:  200m2

Problem:  The felt on the roof area was showing signs of deterioration and as a result water was penetrating into the classroom below.  The work had to be done during term time which meant that stripping the existing roof and the use of hot bitumen materials was a real concern and an alternative had to be found.

Solution:  The deck was power washed to remove all contamination and any blisters in the existing felt were cut open and re-adhered to provide a substrate suitable for coating.  A Tor Coatings' Elastaseal 10 year  system was applied to the roof to provide a durable, waterproof membrane.

 

 

 

 

 

 

 



 